Acronymes
| Name | Formula |
|---|---|
| Cost Variance | CV = EV - AC more |
| Cost Performance Index | CPI = EV/AC
more |
| Estimate At Completion | 1. BAC / CPI — if CPI remains the same
2. AC + ETC — Initial Estimates are flawed
3. AC + BAC – EV — if BAC remains the same
more |
| Estimate To Completion | ETC = EAC -AC
more |
| Earned Value | EV = Actual % complete x BAC
more |
| Schedule Performance Index | SPI = EV/PV
more |
| Schedule Variance | SV = EV – PV
more |
| To-Complete Performance Index | TCPI = (BAC - EV)/(BAC - AC)
more |
| Total Float | Float = LF – EF (or LS – ES)
more |
| Variance at Completion | VAC = BAC – EAC
more |
| PERT | PERT = (P + 4M + O )/ 6
more |
| Standard Deviation (SD) | SD = (P – O) / 6
more |
| Free Float | Free Float = ES of the next activity - EF
more |
| Communication Channels | Communication Channels = n (n-1)/2
more |